Bergtec’s Custom Stop-Logs and Motorised Penstocks for Bucharest’s Water Management System
Problem: Upgrading Bucharest’s Water Infrastructure with Limited Installation Time and Complex Logistics
The project presented multiple challenges due to the nature and scale of the infrastructure:
- Large-Scale Components: The oversized penstocks and stop-logs, measuring up to 4.45 x 2.10 meters, required specialised transportation and handling.
- Restricted Access and Operational Constraints: Installation was limited by specific site access points and strict operation schedules, demanding a rapid, efficient installation approach.
- Structural and Environmental Considerations: Components needed to withstand high pressure, low temperatures, and high humidity levels, while the existing concrete structures required adapted fixation solutions.
These constraints required a robust, custom-engineered solution that could be quickly installed and integrated with Bucharest’s updated water system.
Solution: Bergtec’s Bespoke Stop-Logs and Penstocks with SCADA Integration
To meet the unique demands of the Bucharest water management project, Bergtec provided high-quality, durable equipment tailored to the system’s operational and structural requirements. Key elements of the solution included:
- Custom-Designed Stop-Logs and Penstocks: Constructed from corrosion-resistant marine aluminium and stainless steel, these components were designed to manage water flow and withstand challenging environmental conditions, including low temperatures and high humidity.
- SCADA-Integrated Motorised Penstocks: The penstocks were equipped with SCADA (Supervisory Control and Data Acquisition) systems for automated control, allowing real-time monitoring and precise regulation of water levels in response to heavy rain events.
- Optimised Fixation Standards for Local Conditions: Bergtec adapted its fixation solutions to the site’s structural state, addressing issues with uneven or deteriorated concrete to ensure secure installation.
- Efficient Delivery and Installation: Given the large size of the equipment, “oversized transport” was arranged to deliver the penstocks ready for installation, minimising on-site assembly time and allowing for quick deployment.
- Comprehensive Project Management and Support: Bergtec provided ongoing coordination with local authorities, ensuring seamless integration with the city’s infrastructure. Installation testing confirmed that all components met contract conditions, providing Bucharest with reliable flood protection.
Bergtec’s solution enabled Bucharest to enhance its flood resilience and water management efficiency, integrating new and upgraded systems seamlessly into the existing urban infrastructure.
Project Highlights in Pictures
Results and Impact
Enhanced Water Regulation and Flood Protection for Bucharest
Bergtec’s custom-designed stop-logs and motorised penstocks have improved Bucharest’s flood resilience and water regulation capabilities:
- Reliable Water Management: The SCADA-equipped penstocks enable real-time, automated water regulation, helping to mitigate the impact of heavy rainfall on the city’s stormwater systems.
- Durable, Low-Maintenance Components: Constructed from corrosion-resistant materials and designed for long-term use, the components ensure consistent, low-maintenance operation under harsh conditions.
- Streamlined Installation and Integration: Delivered ready to install, Bergtec’s equipment reduced on-site assembly time, allowing for efficient installation within the project’s constraints.
Through this project, Bergtec enhanced Bucharest’s infrastructure, ensuring the city’s readiness for heavy rains and flood events with reliable, automated water management solutions.
Bergtec offers custom water management and flood protection solutions tailored to urban environments. Discover how our demountable flood barriers, stop-logs, and penstocks can strengthen your infrastructure. Visit our Demountable Flood Barriers page or contact us for a custom solution.